| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 10-2 | Placas laterales de neopreno de 20*20 | dm3 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| NEOPRENO-04 | APOYOS DE NEOPRENO INTEGRAL ASTM-2240-D-60 ( FT = 100 KG / CM2 ) | DM3 | 1.000000 | $130.00 | $130.00 |
| NEOPRENO-04 | APOYOS DE NEOPRENO INTEGRAL ASTM-2240-D-60 ( FT = 100 KG / CM2 ) | DM3 | 1.000000 | $130.00 | $130.00 |
| NEOPRENO-04 | APOYOS DE NEOPRENO INTEGRAL ASTM-2240-D-60 ( FT = 100 KG / CM2 ) | DM3 | 1.000000 | $130.00 | $130.00 |
| Suma de Material | $390.00 | ||||
| Mano de Obra | |||||
| CUAD OC 02 | CUAD. 2 (1 ALBA帽IL + 1 PEON) | JOR | 0.200000 | $876.36 | $175.27 |
| CUAD OC 02 | CUAD. 2 (1 ALBA帽IL + 1 PEON) | JOR | 0.200000 | $876.36 | $175.27 |
| CUAD OC 02 | CUAD. 2 (1 ALBA帽IL + 1 PEON) | JOR | 0.200000 | $876.36 | $175.27 |
| Suma de Mano de Obra | $525.82 | ||||
| Costo Directo | $915.82 |