| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 16 | De fc = 350 kg/cm3 | m³ |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CURAFEST | CURAFESTER ROJO | LT | 1.000000 | $15.00 | $15.00 |
| CONC PREM FC350 | CONCRETO PREMEZCLADO F'C=350 KG/CM2 | M3 | 1.050000 | $1,050.00 | $1,102.50 |
| BOMBEO CONCRETO | BOMBEO DE CONCRETO | m3 | 1.050000 | $120.00 | $126.00 |
| Suma de Material | $1,243.50 | ||||
| Mano de Obra | |||||
| CUAD 014 ALB+4PEON | CUADRILLA 014 OFICIAL ALBAÑIL + 4 PEONES | jor | 0.277000 | $1,343.50 | $372.15 |
| Suma de Mano de Obra | $372.15 | ||||
| Herramienta | |||||
| ANDAM | ANDAMIOS | (%)mo | 0.120000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| VIBRADOR PARA CONCRE | VIBRADOR PARA CONCRETO | Hora | 0.333333 | $50.25 | $16.75 |
| Suma de Equipo | $16.75 | ||||
| Auxiliar | |||||
| CIM EN RAMPAS | CIMBRA EN RAMPAS CON MADERA | m2 | 10.100000 | $129.85 | $1,311.49 |
| Suma de Auxiliar | $1,311.49 | ||||
| Costo Directo | $2,943.88 |