| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 52 | Tubo de cartòn comprimido de 21 cm de diametro | m |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SCT-MAT-ADI-04 | Cimbrafest 19 lt | pza | 0.016100 | $662.04 | $10.66 |
| SCT-MAT-TUBCAR-01 | Tuberia carton comprimido 21cm azul (sonotubo) | ml | 1.100000 | $35.50 | $39.05 |
| SCT-MAT-ACER-01 | Alambre recocido no. 16 | kg | 0.300000 | $17.25 | $5.18 |
| Suma de Material | $54.88 | ||||
| Mano de Obra | |||||
| SCT-CUA-06 | Cuadrilla (1 Albañil + 1 Ayudante) | Jor | 0.152820 | $928.57 | $141.90 |
| Suma de Mano de Obra | $141.90 | ||||
| Herramienta | |||||
| SCT-HERR-01 | Herramienta menor | (%)mo | 0.020000 | $0.00 | $0.00 |
| SCT-HERR-02 | Seguridad industrial | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $196.79 |