| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TERMA-014 | Atizadores Palca e=7/8" | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 313-APL-0108 | PLACA DE ACERO A-36 DE 7/8 (22.2 MM) 174.3 KG/M2 | TON | 0.001050 | $11,250.00 | $11.81 |
| 7018 | SOLDADURA ELECTRODO 7018 | KG | 0.101930 | $29.00 | $2.96 |
| Suma de Material | $14.77 | ||||
| Mano de Obra | |||||
| 1S2E | CUADRILLA No 18 (1 SOLDADOR+2 AY.ESP.) | JOR | 0.001755 | $1,381.44 | $2.42 |
| Suma de Mano de Obra | $2.42 | ||||
| Herramienta | |||||
| %MO5 | EQUIPO DE SEGURIDAD | (%)MO | 0.050000 | $0.00 | $0.00 |
| %MO1 | HERRAMIENTA MENOR | (%)MO | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQECORTE | EQUIPO DE CORTE OXI-CORTE | HOR | 0.000731 | $288.80 | $0.21 |
| EQ-RANGER | SOLDADORA RANGER 305 G LINCOLN ELECTRIC | HR | 0.014048 | $224.56 | $3.15 |
| EQ-007 | EXCAVADORA HIDRAULICA CAT 330 CL | HRA | 0.001291 | $1,075.77 | $1.39 |
| Suma de Equipo | $4.75 | ||||
| Concepto | |||||
| CBPANTICO | PINTURA PRIMARIO ANTICORROSIVO | KG | 1.000000 | $1.86 | $1.86 |
| Suma de Concepto | $1.86 | ||||
| Costo Directo | $23.81 |