| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-04 | ZAPATA AISLADA Z1, DE 20CM DE PERALTE, A BASE DE CONCRETO F'C=200KG/CM2, ARMADO CON VARILLAS DEL No.4 A CADA 20CM AMBOS SENTIDOS, INCLUYE CIMBRA Y DESCIMBRA, ESCUADRAS, Y DESPERDICIOS, COLADO, NIVELADO, VIBRADO, CURADO, ACARREOS, EL PR.. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.400000 | $80.00 | $32.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 1.000000 | $11.00 | $11.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.500000 | $5.00 | $17.50 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.250000 | $10.00 | $2.50 |
| ACERO 04 | ACERO DEL No. 4 | KG | 14.340000 | $6.00 | $86.04 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.430000 | $10.43 | $4.48 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.210000 | $824.77 | $173.20 |
| CONCRETO 01 | BOMBA PARA CONCRETO PREMEZCLADA | M3 | 0.210000 | $100.00 | $21.00 |
| Suma de Material | $347.73 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.050000 | $176.48 | $8.82 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.200000 | $448.80 | $89.76 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.220000 | $448.80 | $98.74 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.040000 | $1,094.57 | $43.78 |
| Suma de Mano de Obra | $241.10 | ||||