| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-E2 | DADO DE 35x35CM POR 1.20 M DE ALTURA, A BASE DE CONCRETO F'C=200KG/CM2, ARMADO CON 8 VARILLAS DEL No.4 (EMPAQUETADOS DE DOS EN DOS) ESTRIBOS DEL No.3 (3/8'') A CADA 15CM, INCLUYE ANCLAS 3/4" REDONDO LISO, CIMBRA Y DESCIMBRA, ESCUADRAS, GANCHOS Y DESPERDICIOS, COLADO, NIVELADO, VIBRADO, CURADO, ACARREOS, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.420000 | $80.00 | $33.60 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.250000 | $11.00 | $2.75 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.000000 | $5.00 | $15.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 1.000000 | $10.00 | $10.00 |
| ACERO 04 | ACERO DEL No. 4 | KG | 13.390000 | $6.00 | $80.34 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.450000 | $10.43 | $4.69 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.161700 | $824.77 | $133.37 |
| Suma de Material | $279.75 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.050000 | $176.48 | $8.82 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.142800 | $448.80 | $64.09 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.200000 | $448.80 | $89.76 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.017000 | $1,094.57 | $18.61 |
| Suma de Mano de Obra | $181.28 | ||||
| Costo Directo | $461.03 |