| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESTR-04 | FABRICACION Y MONTAJE DE ARMADURA DE ALMA ABIERTA A BASE DE ANGULO DE ACERO ESTRUCTURAL (PARA SISTEMA DE TECHO), INCLUYE: LARGUEROS DE MONTEN DE 8X3'' CAL.14, PLACAS DE APOYO, ANCLAJES, SOLDADURA, PRIMER ANTICORROSIVO, DOS MANOS DE ESMALTE ALQUIDALICO COMEX 100, ACARREOS, Y ELEVACION, PRUEBAS DE SOLDADURA, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-ESTRU-17 | PLACA DE ACERO | KG | 1.050000 | $11.50 | $12.08 |
| ACERO-ESTRU-17 | PLACA DE ACERO | KG | 1.050000 | $11.50 | $12.08 |
| ACERO-ESTRU-17 | PLACA DE ACERO | KG | 1.050000 | $11.50 | $12.08 |
| ENERGIA ELECTRICA | ENERGIA ELECTRICA | KW | 0.060000 | $1.80 | $0.11 |
| ENERGIA ELECTRICA | ENERGIA ELECTRICA | KW | 0.060000 | $1.80 | $0.11 |
| ENERGIA ELECTRICA | ENERGIA ELECTRICA | KW | 0.060000 | $1.80 | $0.11 |
| SOLDADURA 7018 | SOLDADURA 70/18 | KG | 0.010000 | $22.00 | $0.22 |
| SOLDADURA 7018 | SOLDADURA 70/18 | KG | 0.010000 | $22.00 | $0.22 |
| SOLDADURA 7018 | SOLDADURA 70/18 | KG | 0.010000 | $22.00 | $0.22 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.007000 | $29.00 | $0.20 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.007000 | $29.00 | $0.20 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.007000 | $29.00 | $0.20 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 0.005000 | $4.05 | $0.02 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 0.005000 | $4.05 | $0.02 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 0.005000 | $4.05 | $0.02 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.000500 | $32.00 | $0.02 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.000500 | $32.00 | $0.02 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.000500 | $32.00 | $0.02 |
| Suma de Material | $37.93 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 42 | (1 Pailero + 1 Soldador + 2 ayudantes A). | Jor | 0.009930 | $820.43 | $8.15 |
| CUADRILLA NO. 42 | (1 Pailero + 1 Soldador + 2 ayudantes A). | Jor | 0.009930 | $820.43 | $8.15 |
| CUADRILLA NO. 42 | (1 Pailero + 1 Soldador + 2 ayudantes A). | Jor | 0.009930 | $820.43 | $8.15 |
| Suma de Mano de Obra | $24.44 | ||||
| Equipo | |||||
| MAQ. SOLDAR EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.008000 | $6.75 | $0.05 |
| MAQ. SOLDAR EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.008000 | $6.75 | $0.05 |
| MAQ. SOLDAR EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.008000 | $6.75 | $0.05 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.008000 | $0.59 | $0.00 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.008000 | $0.59 | $0.00 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.008000 | $0.59 | $0.00 |
| ESMERILADORA | ESMERILADORA | HR | 0.005000 | $19.29 | $0.10 |
| ESMERILADORA | ESMERILADORA | HR | 0.005000 | $19.29 | $0.10 |
| ESMERILADORA | ESMERILADORA | HR | 0.005000 | $19.29 | $0.10 |
| GRUA 15 TON | GRUA 15 TON | HR | 0.004000 | $825.00 | $3.30 |
| GRUA 15 TON | GRUA 15 TON | HR | 0.004000 | $825.00 | $3.30 |
| GRUA 15 TON | GRUA 15 TON | HR | 0.004000 | $825.00 | $3.30 |
| Suma de Equipo | $10.37 | ||||
| Costo Directo | $72.73 |