| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-12 F | TRINCHERA DE 60X60CM DE SECCION, CON MURETES DE CONCRETO F'C=200KG/CM2 DE 10CM DE ESPESOR, ARMADO CON VARILLA DEL No.3 (3/8'') A CADA 20CM AMBOS SENTIDOS, ACABADO PULIDO, INCLUYE ACARREOS LOCALES, EL PRECIO INCLUYE: MATERIALES, MANO DE OBRA Y HERRAMIENTA. NO INCLUYE EXCAVACION NI RELLENO. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.650000 | $80.00 | $52.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 1.500000 | $11.00 | $16.50 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 2.250000 | $5.00 | $11.25 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.250000 | $10.00 | $2.50 |
| ACERO 03 | ACERO DEL # (3/) | KG | 12.287000 | $6.00 | $73.72 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.360000 | $10.43 | $3.75 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.210000 | $824.77 | $173.20 |
| Suma de Material | $332.93 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.250000 | $176.48 | $44.12 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.150000 | $448.80 | $67.32 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.350000 | $448.80 | $157.08 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.035000 | $1,094.57 | $38.31 |
| Suma de Mano de Obra | $306.83 | ||||
| Costo Directo | $639.76 |