| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 31421 | CHAFLAN DE CONCRETO F´C=150 KG/CM2 EN AZOTEA DE 10 CM. DE ANCHO ALTO ACABADO FINO PARA RECIBIR IMPERMEABILIZANTE. INCLUYE: PREPARACION DE LA SUPERFICIE | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MURO-TABI-000 | TABIQUE COMUN DE BARRO ROJO RECOCIDO DE 7 X 14 X 28 CM | millar | 0.005000 | $2,200.00 | $11.00 |
| Suma de Material | $11.00 | ||||
| Mano de Obra | |||||
| 2MOCU-005 | Cuadrilla No 5 (1 Albañíl + 1 Ayudante general ) | Jor | 0.040000 | $888.17 | $35.53 |
| Suma de Mano de Obra | $35.53 | ||||
| Auxiliar | |||||
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.006000 | $1,011.93 | $6.07 |
| 03-0670 | LECHADA CEMENTO GRIS-AGUA | m3 | 0.000200 | $2,619.37 | $0.52 |
| OC-AUX3 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | M3 | 0.004000 | $64.90 | $0.26 |
| Suma de Auxiliar | $6.86 | ||||
| Costo Directo | $53.38 |