| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 100 NIVEL-04 | CASTILLOS K2 ARMEX 15*20-4 1er NIVEL F'C= 200KG/CM2 ACABADO COMUN | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ARMEX 15X20 | armex | ml | 1.100000 | $13.00 | $14.30 |
| AGUA | AGUA ACARREO INTERNO | M3 | 0.060000 | $40.00 | $2.40 |
| Suma de Material | $16.70 | ||||
| Mano de Obra | |||||
| CUADRILLA NO.06 | (1 OFICIAL ALBAÑIL + 1 PEON) | JOR | 0.096465 | $642.91 | $62.02 |
| Suma de Mano de Obra | $62.02 | ||||
| Herramienta | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 0.300000 | $170.37 | $51.11 |
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.023635 | $903.30 | $21.35 |
| Suma de Auxiliar | $72.46 | ||||
| Costo Directo | $151.18 |