| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 027 | CONSTRUCCION DE GUARNICION TIPO L, DE 15 CM. DE ESPESOR POR 30 CM. DE ALTO, CONCRETO F'C= 200 KG/CM2 | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-04 | CONCRETO PREMEZCLADO DE F'C= 200 KG/CM2. | M3 | 0.110000 | $1,000.00 | $110.00 |
| ALAMBRE REC. | ALAMBRE RECOCIDO | KG | 0.300000 | $13.50 | $4.05 |
| DIESEL | DIESEL | LT | 0.500000 | $5.60 | $2.80 |
| Suma de Material | $116.85 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.090909 | $634.95 | $57.72 |
| Suma de Mano de Obra | $57.72 | ||||
| Auxiliar | |||||
| BAS -CIMMET | CIMBRA METALICA DE 50 CMS DE ALTURA | ml | 0.030530 | $326.01 | $9.95 |
| Suma de Auxiliar | $9.95 | ||||
| Costo Directo | $184.53 |