| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TUFO03 | TUBO FOFO TISA TAR O EQUIVALENTE TRAMO DE 1.52 M 15 CM | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO TISA TAR 150MM | TUBO TISA TAR 150 MM DE 1.5MTS | PZA | 1.050000 | $394.00 | $413.70 |
| COPLE TAR 151 MM | COPLE TAR 151 MM | PZA | 1.000000 | $78.00 | $78.00 |
| ABRZ T/PERA 150MM | ABRAZ T/PERA 150 MM | PZA | 1.000000 | $25.00 | $25.00 |
| TAQU. PERNO HDI 1/4" | INCLUYE: FULMINANTE PARA PISTOLA D-450 | PZA | 1.000000 | $6.20 | $6.20 |
| CARGAS HILTI ROJA | CARGA HILTI ROJA | PZA | 1.000000 | $0.90 | $0.90 |
| ESPARRAGO 1/4" | ESPARRAGO 1/4" | ML | 1.000000 | $5.60 | $5.60 |
| TUERCA GALV. 1/4" | TUERCA GALV. 1/4" | PZA | 1.000000 | $0.10 | $0.10 |
| Suma de Material | $529.50 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.083330 | $151.39 | $12.62 |
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.220000 | $647.77 | $142.51 |
| Suma de Mano de Obra | $155.12 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.200000 | $15.48 | $3.10 |
| Suma de Auxiliar | $3.10 | ||||
| Costo Directo | $687.72 |