| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 5.10 | CIMBRA COMUN EN CIMENTACION | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO REF. #2 ALAMB | ALAMBRON DE 1/4" | kg | 0.100000 | $13.43 | $1.34 |
| CIMBRAPLAY | CIMBRAPLAY 16 MM | m2 | 0.080000 | $81.79 | $6.54 |
| MADERA DE PINO DE 3A | MADERA DE PINO DE 3a. | PT | 1.750000 | $9.12 | $15.96 |
| CLAVO CON CABEZA DE | Clavo con cabeza de 3" .004KG/PZA PROM. | kg | 0.200000 | $16.12 | $3.22 |
| DIESEL | DIESEL | litro | 0.500000 | $4.31 | $2.16 |
| Suma de Material | $29.23 | ||||
| Mano de Obra | |||||
| CUADRILLA -16 | (1 OF. CARPINTERO O.N. + 1 AYTE.) | JOR | 0.070000 | $742.86 | $52.00 |
| Suma de Mano de Obra | $52.00 | ||||
| Costo Directo | $81.23 |