| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IS-327 | SUMINISTRO E INSTALACION DE DRENAJE PARA EVAPORADOR DE EQUIPO DE AIRE ACONDICIONADO, INCLUYE: MATERIAL, MANO DE OBRA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA INSTALACION. | PZA* |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO CPVC 13 MM | TUBO DE CPVC CTS 13MM (3.05MTS) | TRAMO | 1.050000 | $43.61 | $45.79 |
| CODO CPVC 13 MM | CODO CPVC CTS (2300) 90-13MM | PZA | 6.000000 | $1.19 | $7.14 |
| PEG TANGIT NARANJA | CEMENTO CPVC NARANJA (240ML)TANGIT | BOTE | 0.108000 | $65.25 | $7.05 |
| INS LIMP P/PVC | LIMPIADOR PVC 250ML | BOTE | 0.080000 | $35.00 | $2.80 |
| INS ESTOPA | ESTOPA | KG | 0.070340 | $17.50 | $1.23 |
| INS LIJA FINA ESM | LIJA FINA ESMERIL | PZA | 0.100000 | $9.74 | $0.97 |
| Suma de Material | $64.98 | ||||
| Mano de Obra | |||||
| CUAD PLOMEROS | CUADRILLA DE PLOMEROS | JOR | 0.333333 | $694.26 | $231.42 |
| Suma de Mano de Obra | $231.42 | ||||
| Costo Directo | $296.40 |