| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| LE 04.01 | LOSA DE CONCRETO DE 10 CMS DE ESPESOR F¨C=300 KG/CM2 ARMADA CON UNA PARRILLA DE ACERO DEL No.3 @30 | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO DE REFUERZO | ACERO DE REFUERZO EN SOTANO DEL No. 3 AL 12 | KG | 5.680000 | $7.00 | $39.76 |
| ALAMBRE RECOC 18 | ALAMBRE RECOCIDO # 18 | KG | 0.178560 | $14.87 | $2.66 |
| CONC.PREMEZ.F´C=300 | Concreto Premezclado F'c=300 Kg/cm2 A.M. 3/4" rev 13-14 | M3 | 0.121000 | $730.00 | $88.33 |
| REVENIMIENTO | REVENIMIENTO DE CONCRETO 14 Y 18 | M3 | 0.121000 | $90.00 | $10.89 |
| RESISTENCIA 7 DIAS | Resistencia rapida a 7 dias (base cemento) | M3 | 0.121000 | $103.00 | $12.46 |
| AGUA | Agua potable | M3 | 0.050000 | $40.00 | $2.00 |
| POLIN 3.5" X 3.5" | MADERA DE PINO DE 3A. EN POLIN DE 3.5" X 3.5" | PT | 1.500000 | $7.50 | $11.25 |
| BARROTE 1.5" X 3.5" | MADERA DE PINO DE 3A. EN BARROTE DE 1.5" X 3.5" | PT | 1.500000 | $5.60 | $8.40 |
| CIMBRAPLAY 16 MM | cimbraplay de 16 mm | M2 | 0.333000 | $90.00 | $29.97 |
| CLAVOS | VARIAS MEDIDAS NORMAL | KG | 0.300000 | $17.50 | $5.25 |
| DIESEL | diesel pemex | Lt | 0.580000 | $6.00 | $3.48 |
| Suma de Material | $214.45 | ||||
| Mano de Obra | |||||
| CUAD 18 | Cuadrilla No. 18 ( 1 Of. Fierrero + 1Ayudante). | jor | 0.015870 | $794.60 | $12.61 |
| CUAD 05 | ( 1 ALBAÑIL + 5 PEONES ) | jor | 0.006370 | $2,073.42 | $13.21 |
| CUAD 11 | (1 Of. Carpintero O.N. + 1Ayte). | jor | 0.143472 | $794.60 | $114.00 |
| Suma de Mano de Obra | $139.82 | ||||
| Herramienta | |||||
| HE003 | Andamios metálicos tipo torre | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| BOMBA PLUMA | Bomba pluma para concreto con diámetro hasta 4" (102mm) | M3 | 0.121000 | $90.00 | $10.89 |
| VIBRADOR | Vibrador para concreto Mot. Kohler 4 H.Con operador. | HR | 0.075000 | $53.08 | $3.98 |
| Suma de Equipo | $14.87 | ||||
| Costo Directo | $369.14 |