| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EXTRA 2 | SUMINISTRO Y TENDIDO DE TUBERIA ADS DE 60 CM. DE DIAM. PARA ALCANTARILLA EN KM 29+720, INCLUYE: TRAZO, EXCAVACION EN MATERIAL TIPO A, DEMOLICION EN MATERIAL "C" , ACARREOS, PLANTILLA, RELLENO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| EXTRA-DEMOL | DEMOLICION EN MATERIAL "C" CON EXCAVADORA Y MARTILLO | M3 | 22.082680 | $817.76 | $18,058.33 |
| TUBO ADS 60 CM DIAM. | TUBO ADS DE 60 CM. | ML | 54.000000 | $296.00 | $15,984.00 |
| CONCRETO-01 | RELLENO FLUIDO | M3 | 60.000000 | $850.00 | $51,000.00 |
| Suma de Material | $85,042.33 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMERO | 1 PLOMERO + 1 AYUD. | jor | 9.000000 | $643.20 | $5,788.80 |
| Suma de Mano de Obra | $5,788.80 | ||||
| Equipo | |||||
| RETROEXCAVADORA | RETROEXCAVADORA | HR | 10.883580 | $130.34 | $1,418.57 |
| CAMION DE VOLTEO. | CAMION DE VOLTEO | HR | 3.543480 | $171.19 | $606.61 |
| Suma de Equipo | $2,025.17 | ||||
| Concepto | |||||
| 6.8 009-102D1 | Para el primer kilometro | M3 | 30.438200 | $4.41 | $134.23 |
| 047-D.02 B | RELLENO EXEDENTE DE PROYECTO PARA PROTECCION DE OBRAS DE DRENAJE (APROCHES) | m3 | 20.699010 | $31.29 | $647.67 |
| N.CTR.CAR.1.01.007-1 | EXCAVACION EXEDENTE DE PROYECTO PARA ESTRUCTURA DE OBRAS DE DRENAJE. | M3 | 23.403190 | $17.40 | $407.22 |
| EXTRA-PLANT | PLANTILLA DE MATERIAL INERTE | M3 | 4.978860 | $109.70 | $546.18 |
| Suma de Concepto | $1,735.30 | ||||
| Costo Directo | $94,591.61 |