| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 37 | SUMINISTRO Y HECHURA DE COLECTOR PLUVIAL DE PISO Y MUROS DE CONCRETO DE 15 CMS CON PARRILLA ARMADA DE 3/8" CADA 25 CM, DE 2.00 X 0.50 X 1.00 MTS, MEDIDAS INTERIORES, CON TAPA DE REJILLA IRWIN PINTADA CON PRIMARIO Y ACABADO NEGRO MATE CON MARCO Y CONTRAMARCO, INCLUYE: EQUIPOS, HERRAM, M.O. , LIMPIEZA EN EL ÁREA DE TRABAJO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C 250 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL F'C = 250 KG/CM2, T.M.A. 3/4", | M3 | 0.550000 | $975.00 | $536.25 |
| AGREGADO-003 | AGUA ACARREO INTERNO | M3 | 0.080000 | $25.00 | $2.00 |
| ACERO DIF. DIAM. | ACERO REF.VAR.DIAM. | kg | 17.500000 | $8.61 | $150.68 |
| ALAMBRE REC. | ALAMBRE RECOCIDO | KG | 0.750000 | $10.00 | $7.50 |
| CIMBRAPLAY 16 MM. | CIMBRAPLAY 16 MM | m2 | 1.000000 | $86.00 | $86.00 |
| MADERA DE PINO 3A | PT | 8.500000 | $7.50 | $63.75 | |
| CLAVO | Kg | 0.500000 | $16.00 | $8.00 | |
| DIESEL | DIESEL | LITRO | 2.050000 | $7.00 | $14.35 |
| REJILLA IRVIG | M2 | 2.000000 | $1,250.00 | $2,500.00 | |
| MARCO Y CONTR.METALI | KG | 42.000000 | $25.00 | $1,050.00 | |
| CHAFLAN 1" | CHAFLAN 1" | ML | 8.000000 | $3.00 | $24.00 |
| Suma de Material | $4,442.53 | ||||
| Mano de Obra | |||||
| CUADRILLA 09 | (1 OF. ALBAÑIL + 1 PEON) | jor | 0.125000 | $671.52 | $83.94 |
| CUADRILLA NO. 10 | (1 OF. CARPINTERO DE OBRA NEGRA + 2 AYUDANTES ) | JOR | 0.600000 | $805.10 | $483.06 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | JOR | 0.166700 | $645.41 | $107.59 |
| Suma de Mano de Obra | $674.59 | ||||
| Equipo | |||||
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOTOR KOHLE, DE 4 H.P., CON OPERADOR. | HORA | 0.987031 | $51.32 | $50.65 |
| Suma de Equipo | $50.65 | ||||
| Costo Directo | $5,167.77 |