| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 80 | ZAPATAS DE 150 X 300 CM Y 20 CM DE ALTURA (D-431-01-4-4860) | Pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.990000 | $1,568.24 | $1,552.56 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.275000 | $950.72 | $261.45 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 1.265000 | $134.17 | $169.73 |
| ACERO CIMEN. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.048730 | $8,944.41 | $435.86 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 1.408000 | $151.18 | $212.86 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 6.547200 | $36.03 | $235.90 |
| Suma de Auxiliar | $2,868.35 | ||||
| Costo Directo | $2,868.35 |