| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 89 | ZAPATAS DE 210 X 210 CM Y 35 CM DE ALTURA (D-431-01-4-4120, E-431-01-4-4095) | Pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 1.694000 | $1,568.24 | $2,656.60 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.264000 | $950.72 | $250.99 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 1.958000 | $134.17 | $262.70 |
| ACERO CIMEN. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.054120 | $8,944.41 | $484.07 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 3.234000 | $151.18 | $488.92 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 6.388800 | $36.03 | $230.19 |
| Suma de Auxiliar | $4,373.47 | ||||
| Costo Directo | $4,373.47 |