| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 524 | 10” DIAM. (254 MM) LIMPIEZA | METROS |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.042890 | $741.54 | $31.80 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.104610 | $121.57 | $12.72 |
| PIN012 | ACABADO RA-26 | LT | 0.357420 | $143.89 | $51.43 |
| PIN006 | SOLVENTE 50/50 | LT | 0.005230 | $8.14 | $0.04 |
| PIN007 | SOLVENTE 80/20 | LT | 0.071480 | $11.29 | $0.81 |
| CON-006 | TRAPO DE ALGODON | KG | 0.017160 | $46.27 | $0.79 |
| MA-307 | THINNER | LT | 0.085780 | $11.96 | $1.03 |
| Suma de Material | $98.62 | ||||
| Mano de Obra | |||||
| CUAD017 | CUADRILLA SAND BLASTERO-PINTOR + AYUDANTE | jor | 0.050460 | $832.18 | $41.99 |
| Suma de Mano de Obra | $41.99 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ012 | EQUIPO PARA SAND BLAST Y PINTURA | hora | 0.504600 | $141.60 | $71.45 |
| Suma de Equipo | $71.45 | ||||
| Costo Directo | $212.06 |