| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 82 | ZAPATAS DE 160 X 160 CM Y 20 CM DE ALTURA (D-431-01-4-4837) | Pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.561000 | $1,568.24 | $879.78 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.154000 | $950.72 | $146.41 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.715000 | $134.17 | $95.93 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.018850 | $9,192.72 | $173.28 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 1.408000 | $151.18 | $212.86 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 3.814800 | $36.03 | $137.45 |
| Suma de Auxiliar | $1,645.72 | ||||
| Costo Directo | $1,645.72 |