| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 88 | ZAPATAS DE 350 X 350 CM Y 40 CM DE ALTURA (E-431-01-4-4095, D-431-01-4-4120) | Pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 5.390000 | $1,568.24 | $8,452.81 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.712800 | $950.72 | $677.67 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 6.102800 | $134.17 | $818.81 |
| ACERO CIMEN. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.163856 | $8,944.41 | $1,465.60 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 6.160000 | $151.18 | $931.27 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 17.107200 | $36.03 | $616.37 |
| Suma de Auxiliar | $12,962.54 | ||||
| Costo Directo | $12,962.54 |