| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 67 | DE 150 X 150 CM Y 160 CM DE PROFUNDIDAD | Pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 1.975050 | $1,568.24 | $3,097.35 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.128000 | $950.72 | $121.69 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 2.103050 | $134.17 | $282.17 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 9.600000 | $151.18 | $1,451.33 |
| ACERO ESTRUC. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.098310 | $9,398.41 | $923.96 |
| TAPA REGISTRO | TAPA PARA REGISTRO | PZA | 1.000000 | $1,765.23 | $1,765.23 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 3.600000 | $36.03 | $129.71 |
| Suma de Auxiliar | $7,771.43 | ||||
| Costo Directo | $7,771.43 |