| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA EN TRABE V | CIMBRA EN TRABE V | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRAPLAY16 MM | CIMBRAPLAY DE 16MM EN M2 | M2 | 0.170000 | $96.00 | $16.32 |
| MADERAPOLIN44 | MADERA DE PINO DE 3 ERA. EN EN POLIN DE 4" X 4" | PT | 1.100000 | $10.10 | $11.11 |
| CLAVO (VARIAS MED.) | CLAVO PARA MADERA VARIAS MEDIDAS | KG | 0.100000 | $17.00 | $1.70 |
| DESMOLTANTESIKA | DESMOLDANTE SEPAROL DE SIKA EN LTS | LT | 0.500000 | $13.80 | $6.90 |
| CHAF01 | CHAFLAN 1" | ML | 1.000000 | $3.20 | $3.20 |
| Suma de Material | $39.23 | ||||
| Mano de Obra | |||||
| MO8 | (1 OFICIAL CARPINTERO + 1 AYUDANTE) | JOR | 0.166667 | $743.55 | $123.93 |
| Suma de Mano de Obra | $123.93 | ||||
| Costo Directo | $163.16 |