| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 136 | DE 25 X 90 CM, (D-431-01-4-4111) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.247500 | $1,568.24 | $388.14 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.247500 | $134.17 | $33.21 |
| CIMBRA COMUN LOSAS | CIMBRA COMUN EN MUROS, COLUMNAS, TRABES Y LOSAS. | M2 | 2.530000 | $176.10 | $445.53 |
| ACERO ESTRUC. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.012380 | $9,398.41 | $116.35 |
| ACERO ESTRUC. NO. 5 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA FY=4200 KG/CM2. DEL No. 5 ( 5/8" ) DE DIAM. | TON | 0.020592 | $8,721.50 | $179.59 |
| Suma de Auxiliar | $1,162.82 | ||||
| Costo Directo | $1,162.82 |