| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 97 | DE 18 X 40 CM (D-431-01-4-4720) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.079200 | $1,568.24 | $124.20 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.015400 | $950.72 | $14.64 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.094600 | $134.17 | $12.69 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 0.880000 | $151.18 | $133.04 |
| ACERO CIMEN. NO. 6 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 6 ( 3/4" ) DE DIAM. | TON | 0.006860 | $8,410.57 | $57.70 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.004766 | $9,192.72 | $43.81 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 0.088910 | $36.03 | $3.20 |
| Suma de Auxiliar | $389.29 | ||||
| Costo Directo | $389.29 |