| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ELEC-13)) | REGISTRO DE CONCRETO F'C=100 KG/CM2 DE 0.60X0.60X0.60 PARA ELECTRIFICACION, INCLUYE: MATERIALES SUMINISTRO, ACARREO, COLOCACION Y HERRAMIENTA. | PZA. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.564300 | $824.77 | $465.42 |
| MARCO MET, P/REG. | MARCO MET, P/REG. | PZA | 1.000000 | $210.00 | $210.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 2.600000 | $5.00 | $13.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $11.00 | $1.10 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 1.120000 | $80.00 | $89.60 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 2.000000 | $10.00 | $20.00 |
| ACERO 03 | ACERO DEL # (3/) | KG | 11.000000 | $6.00 | $66.00 |
| ACERO-022 | ALAMBRON | KG | 0.750000 | $6.00 | $4.50 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.100000 | $10.43 | $1.04 |
| Suma de Material | $870.66 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 1.000000 | $440.17 | $440.17 |
| Suma de Mano de Obra | $440.17 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.200000 | $15.98 | $3.20 |
| Suma de Equipo | $3.20 | ||||
| Costo Directo | $1,314.03 |