| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 949 | INGENIERIA DE DETALLE PARA LA INFRAESTRUCTURA DEL POZO, INCLUYE: DISEÑO DE EQUIPO DE BOMBEO, DISEÑO ELECTRICO E INSTALACIONES, DISEÑO CIVIL ESTRUCTURAL, DISEÑO DE TUBERIAS, DISEÑO DE INSTRUMENTACION, CONTROL E INSTALACIONES, DISEÑO SISTEMA DE TRATAMIENTO DE AGUA E INSTALACIONES | PAQUETE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PAP006 | PAPEL COATED 42" H.P. C6559A PARA PLOTTER | ROLLO | 6.000000 | $979.51 | $5,877.06 |
| PAP007 | PAPEL HEAVY WEIGHT 24" HP 51648D | ROLLO | 3.000000 | $922.53 | $2,767.59 |
| PAP001 | COMPACT DISC ESCRIBIBLE 1-32X COMPATIBLE (CD-R) 80 MIN. - 700 Mb | PZA | 5.000000 | $22.20 | $111.00 |
| PAP008 | DISCO DE 3 1/2" MF 2HD PREFORMATEADO IBM 1.44 Mb | PZA | 5.000000 | $14.80 | $74.00 |
| PAP002 | CARTUCHO DE TINTA NEGRO HPC4844 A PARA PLOTTER DJ500 | PZA | 2.000000 | $539.38 | $1,078.76 |
| PAP003 | CARTUCHO DE TINTA CYAN HP C4911 A PARA PLOTTER DJ500 | PZA | 2.000000 | $592.00 | $1,184.00 |
| PAP004 | CARTUCHO DE TINTA MAGENTA HP C4912 PARA PLOTTER DJ500 | PZA | 2.000000 | $592.00 | $1,184.00 |
| PAP005 | CARTUCHO DE TINTA AMARILLO HP C4913 PARA PLOTTER DJ500 | PZA | 2.000000 | $592.00 | $1,184.00 |
| PAP009 | PAPEL BOND BLANCO TAMAÑO CARTA MEDIDAS 216 X 279 mm No. DE PARTE 3M2000 PAQUETES DE 500 HOJAS PESO BASE 75 g/m² MARCA XEROX | PAQ | 8.000000 | $41.11 | $328.88 |
| PAP010 | THONNER NEGRO PARA IMPRESORA | PZA | 1.000000 | $1,324.89 | $1,324.89 |
| PAP011 | LAPIZ 2H MARCA MIRADO O SIMILAR | PZA | 5.000000 | $24.67 | $123.35 |
| PAP012 | PLUMA O BOLIGRAFO COLOR AZUL O NEGRO | PZA | 5.000000 | $24.67 | $123.35 |
| PAP013 | LIBRETA DE NIVEL | PZA | 2.000000 | $41.11 | $82.22 |
| PAP014 | CARPETAS BLANCAS DE 3 ARILLOS DE 3 PULGADAS | PZA | 5.000000 | $115.11 | $575.55 |
| PAP016 | CARTUCHO A COLOR Y NEGRO PARA IMPRESORA A COLOR DOBLE CARTA HP | JGO | 2.000000 | $247.18 | $494.36 |
| Suma de Material | $16,513.01 | ||||
| Mano de Obra | |||||
| CUAD302 | CUADRILLA PARA INGENIERIA DE DETALLE DE POZO PROFUNDO | jor | 20.000000 | $20,028.84 | $400,576.80 |
| Suma de Mano de Obra | $400,576.80 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ401 | CUADRILLA PARA INGENIERIA DE DETALLE DE POZO PROFUNDO | hora | 200.000000 | $58.79 | $11,758.00 |
| Suma de Equipo | $11,758.00 | ||||
| Costo Directo | $428,847.81 |