| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 103 | ZAPATA DE 25 X 200, MURO DE 25 CM DE ESPESOR Y ALTURA VARIABLE, (D-431-01-4-4296, 4297) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONF-C=250KG/CM2.IM | CONCRETO HECHO EN OBRA F'C=250 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 1.694000 | $1,568.24 | $2,656.60 |
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.121000 | $950.72 | $115.04 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 1.815000 | $134.17 | $243.52 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 9.680000 | $151.18 | $1,463.42 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.013552 | $9,192.72 | $124.58 |
| ACERO CIMEN. NO. 4 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 4 ( 1/2" ) DE DIAM. | TON | 0.036520 | $8,944.41 | $326.65 |
| ACERO CIMEN. NO. 5 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 5 ( 5/8" ) DE DIAM. | TON | 0.102274 | $8,564.97 | $875.97 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 2.772000 | $36.03 | $99.88 |
| Suma de Auxiliar | $5,905.66 | ||||
| Costo Directo | $5,905.66 |