| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 19 | DE 40 cm DE ANCHO INTERIOR Y PROFUNDIDAD VARIABLE, (E-431-01-4-4495) | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REJILLA IRVING | REJILLA TIPO IRVING CON SOLERA DE CARGA DE 5X32 mm | m2 | 0.550000 | $719.45 | $395.70 |
| LI11/2X1/4 | ANGULO LI DE ACERO AL CARBON DE 1 1/2" X 1/4" ASTM-A-36 | KG | 7.660000 | $8.16 | $62.51 |
| REDONDO LISO #3 | ANCLA DE ACERO REDONDO LISO # 3 | KG | 0.369600 | $8.16 | $3.02 |
| MAT-CON004 | SOLDADURA NOM H-77 AWS E-6010, 7018 | KG | 0.229800 | $19.18 | $4.41 |
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.019150 | $741.54 | $14.20 |
| MAT-CON001 | OXIGENO | M3 | 0.076600 | $37.41 | $2.87 |
| MAT-CON002 | ACETILENO | KG | 0.038300 | $133.34 | $5.11 |
| MAT-CON003 | DISCO ABRASIVO DE 1/4" | PZA | 0.015320 | $57.55 | $0.88 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.076600 | $121.57 | $9.31 |
| PIN012 | ACABADO RA-26 | LT | 0.091920 | $143.89 | $13.23 |
| MA-307 | THINNER | LT | 0.045960 | $11.96 | $0.55 |
| Suma de Material | $511.77 | ||||
| Mano de Obra | |||||
| CUAD014 | CUADRILLA OPERARIO ESPECIALISTA SOLDADOR + AYUDANTE | jor | 0.019150 | $832.18 | $15.94 |
| CUAD036 | CUADRILLA OPERARIO ESPECIALISTA PAILERO + AYUDANTE | jor | 0.019150 | $832.18 | $15.94 |
| CUAD017 | CUADRILLA SAND BLASTERO-PINTOR + AYUDANTE | jor | 0.019150 | $832.18 | $15.94 |
| Suma de Mano de Obra | $47.81 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ031 | EQUIPO PARA SOLDURA Y CORTE | hora | 0.191500 | $62.95 | $12.05 |
| MAQ012 | EQUIPO PARA SAND BLAST Y PINTURA | hora | 0.191500 | $141.60 | $27.12 |
| Suma de Equipo | $39.17 | ||||
| Auxiliar | |||||
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.029700 | $950.72 | $28.24 |
| CONC. F-C=200KG/CM2. | CONCRETO HECHO EN OBRA F'C=200 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.330000 | $1,453.67 | $479.71 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.359700 | $134.17 | $48.26 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 0.480000 | $36.03 | $17.29 |
| ACERO REFZO NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.015100 | $9,192.72 | $138.81 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 2.200000 | $151.18 | $332.60 |
| ACERO REFZO NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.015100 | $9,192.72 | $138.81 |
| Suma de Auxiliar | $1,183.72 | ||||
| Costo Directo | $1,782.47 |