| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 6 | RELLENO COMPACTADO CON MAQUINA AL 95% P. PROCTOR EN CAPAS NO MAYORES DE 15 CM, CON MATERIAL PRODUCTO DE LA EXCAVACION A UNA ALTURA PROMEDIO DE 0.65 MT. EN AREA COMPACTADA, INCLUYE: CARGA Y ACARREO, VOLUMEN MEDIDO EN CAJA. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.180000 | $40.00 | $7.20 |
| AGUA | AGUA | M3 | 0.180000 | $40.00 | $7.20 |
| Suma de Material | $14.40 | ||||
| Mano de Obra | |||||
| C02-0010 | CUAD. No 1 ( 1 PEON ) | JOR | 0.166667 | $350.67 | $58.45 |
| C02-0010 | CUAD. No 1 ( 1 PEON ) | JOR | 0.166667 | $350.67 | $58.45 |
| Suma de Mano de Obra | $116.89 | ||||
| Equipo | |||||
| ARODILLO | RODILLO VIBRATORIO DYNAPAC, MOD. PR8 MOTOR DE GASOLINA KOHLER K181, 8 HP | hora | 0.142857 | $23.72 | $3.39 |
| ARODILLO | RODILLO VIBRATORIO DYNAPAC, MOD. PR8 MOTOR DE GASOLINA KOHLER K181, 8 HP | hora | 0.142857 | $23.72 | $3.39 |
| Suma de Equipo | $6.78 | ||||
| Costo Directo | $138.07 |