| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.1 3 | ZAPATA DE CIMENTACION CORRIDA (Z3) INCLUYE CIMBRA Y DESCIMBRA ANCHO=120 CM PERALTE=20 CM FY'=4200 KG/CM2 ARMADA CON 4 VARILLAS DEL No. 3 EN SENTIDO LONGITUDINAL Y CON VARILLAS DEL # 3 @ 15 CMS. EN SENTIDO LONGITUDINAL GALV. POR INMERSION EN CALIENTE.CONCRETO F'C=250 KG/CM2-3/4" PREMEZCLADO, BOMBEADO, VIBRADO Y CURADO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GALVANIZADO POR INME | KG | 13.970000 | $3.00 | $41.91 | |
| AGUA | M3 | 0.600000 | $45.00 | $27.00 | |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.025000 | $110.00 | $2.75 |
| Suma de Material | $71.66 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 0.400000 | $72.29 | $28.92 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.014000 | $13,029.10 | $182.41 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.252000 | $1,181.25 | $297.68 |
| Suma de Concepto | $509.00 | ||||
| Costo Directo | $580.66 |