| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.1 4 | CONTRATRABE DE CIMENTACION (TC1) INCLUYE CIMBRA Y DESCIMBRA SECCION 0.30 X 0.15 M REFORZADO CON 4 VARILLAS DE #3 GALV. Y EST. # 2 @ 20CMS POR INMERSION EN CALIENTE CONCRETO F'C=250 KG/CM2-3/4" PREMEZCLADO, BOMBEADO , VIBRADO Y CURADO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GALVANIZADO POR INME | KG | 4.530000 | $3.00 | $13.59 | |
| AGUA | M3 | 0.600000 | $45.00 | $27.00 | |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.023000 | $110.00 | $2.53 |
| Suma de Material | $43.12 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 0.600000 | $72.29 | $43.37 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.005000 | $13,029.10 | $65.15 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.023000 | $1,181.25 | $27.17 |
| Suma de Concepto | $135.69 | ||||
| Costo Directo | $178.81 |