| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4.1-29 | SUMINISTRO E INSTALACION DE TABLERO DE DISTRIBUCION I-LONE LA36400, 220/127, 3 F., 4 H., 60 HZ., CALIDAD SQUARE D O SUPERIOR PARA SOBREPONER CORRESPONDIENTE A ALUMBRADO, CONTACTOS NORMALES Y ALIMENTACION A UPS., CON INTERRUPTOR TERMOMAGNETICO PRINCIPAL DE 3 X 400 AMP. 2 INTERRUPTORES TERMOMAGNETICOS DERIVADOS DE 3 X 50 AMP.ITM (FA32050), 3 INTERRUPTORES TERMOMAGNETICOS DERIVADOS DE 3 X 70 AMP. ITM (FH36070) 1 INTERRUPTOR TERMOMAG. DERIVADOS DE 3 X 100 A. ITM (FA 32100), UN INTERRUPTOR TERMOMAG. DERIVADO DE 3 X 125 A. ITM (KA36125) CALIDAD SQUARE-D O SUPERIOR. INCLUYE : MATERIAL, MANO DE OBRA, HERRAMIENTA Y DEMAS CARGOS CORRESPONDIENTES POR UNIDAD DE OBRA TERMINADA. ( P.U.O.T. ) | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| T.I LINE LA-400M-102 | TABLERO TIPO I LINE CAT-LA-400M-102A 3 FASES, 4 HILOS MARCA SQUARE´D | PZA | 1.000000 | $12,500.00 | $12,500.00 |
| CINTA 33 SCOTCH- | CINTA DE AISLAR No. 33 MARCA SUPER 3-M | PZA | 0.500000 | $25.39 | $12.70 |
| CINCHO PLASTICO 30CM | CINCHO PLASTICO 30CM | PZA | 50.000000 | $0.36 | $18.00 |
| VARILLA ROSCADA 1/2" | VARILLA ROSCADA DE 1/2" TRAMO DE 3 MTS | PZA | 1.200000 | $15.30 | $18.36 |
| UNICANAL U-30 | UNICANAL U-30 CLEVIS | ML | 2.000000 | $25.10 | $50.20 |
| TAQUETE SCI 1/2" | TAQUETE TIPO SCI DE 1/2" CLEVIS | PZA | 4.000000 | $16.20 | $64.80 |
| ROLDANA DE 1/2" | ROLDANA DE 1/2" | PZA | 8.000000 | $0.28 | $2.24 |
| BROCA P/CONCRETO 5/8 | BROCA PARA CONCRETO DE 5/8" DE DIAMETRO X 6" DE LONGITUD Y 3/8" DE ZANCO | PZA | 0.040000 | $67.06 | $2.68 |
| INT. TERM. FAL 3X50A | INT. TERM. FAL 3X50A | PZA | 2.000000 | $2,295.72 | $4,591.44 |
| INT. TERM. FAL 3X70A | INT. TERM. FAL 3X70A | PZA | 3.000000 | $2,639.30 | $7,917.90 |
| INT. TERM. FAL 3X100 | INT. TERM. FAL 3X100 | PZA | 1.000000 | $2,639.30 | $2,639.30 |
| INT. TERM. KAL 3X125 | INT. TERM. KAL 3X125 | PZA | 1.000000 | $6,627.21 | $6,627.21 |
| Suma de Material | $34,444.83 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | JOR | 3.500000 | $769.02 | $2,691.57 |
| CUADRILLA ALTA TENS. | Cuadrilla Electrica Alta Tension | JOR | 1.500000 | $1,892.49 | $2,838.74 |
| CUADRILLA NO. 01 | (1 PEON) | jor | 0.500000 | $233.45 | $116.73 |
| CUAD MANIOBR INST | CUADRILLA DE MANIOBRAS Y MONTAJES | JOR | 0.250000 | $1,411.39 | $352.85 |
| Suma de Mano de Obra | $5,999.88 | ||||
| Equipo | |||||
| TALADRO ROTOMARTILLO | TALADRO ROTOMARTILLO MCA. DWALT 5/8"-1/2" | HR | 0.020000 | $0.45 | $0.01 |
| GRUA 20 TON | GRUA DE 20 TON | HR | 2.000000 | $463.47 | $926.94 |
| Suma de Equipo | $926.95 | ||||
| Costo Directo | $41,371.65 |