| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.1.3.1 | SUMINISTRO, INSTALACION Y PRUEBA DE REDUCCION HIDRAULICA CEMENTAR BUSHING DE 100 A 75 MM. INCLUYE TODO EL MATERIAL NECESARIO PARA ASEGURAR SU HERMETICIDAD Y CORRECTA INSTALACION | PZ |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0309272 | REDUC. HID. CEM. BUSH. 100-75 MM. | PZ | 1.000000 | $4.55 | $4.55 |
| 9700130 | LIMPIADOR REXOLIT .500 LTS. | PZ | 0.220000 | $6.86 | $1.51 |
| 9700254 | CEMENTO AGRICOLA 480 ML | PZ | 0.365000 | $22.48 | $8.21 |
| Suma de Material | $14.26 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA No.24 (1.00 OF. INST.+ 1.00 AY.ESP.) | jor | 0.020000 | $561.11 | $11.22 |
| Suma de Mano de Obra | $11.22 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039 | F-150 PICK-UP XL CAMION SERIE 3FTDF1729XMA29405 | hora | 0.005000 | $158.90 | $0.79 |
| Suma de Equipo | $0.79 | ||||
| Costo Directo | $26.28 |