| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.5.1 12 | ESCALON DE CONCRETO HUELLA Y PERALTE MARTERINADO COLOR GRIS DE 30 CMS DE ANCHO. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.019000 | $781.40 | $14.85 |
| GRANO DE MARMOL | kg | 7.000000 | $3.00 | $21.00 | |
| PVC DE 2" | ML | 1.000000 | $8.33 | $8.33 | |
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 2.200000 | $5.90 | $12.98 |
| CLAVO | CLAVO | KG | 0.080000 | $13.50 | $1.08 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.090000 | $16.95 | $1.53 |
| COLOR P/CONCRETO | KG | 1.500000 | $12.00 | $18.00 | |
| Suma de Material | $77.76 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.222220 | $576.23 | $128.05 |
| Suma de Mano de Obra | $128.05 | ||||
| Costo Directo | $205.81 |