| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 2.2.1.10 | NERVADURA EN ESTRUCTURA (N6) SECCION = 20 X25 CM REFORZADA CON 5 VAR. #3, 2 BASTONES DEL No. 5 X 5 ML Y EST. #2 @ 20CM , DE ACERO FY'=4200 KG/CM2 GALV. POR INMERSION EN CALIENTE, CONCRETO PREMEZCLADO F'C=250 KG/CM2-3/4" BOMBEADO Y VIBRADO CON ACELERANTE | ML |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 250 | CONCRETO PREMEZCLADO BOMBEABLE DE 250 KG/CM2, INCLUYE: CONCRETO CPO, REVENIMIENTO 12-14. | M3 | 0.052000 | $949.00 | $49.35 |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.052000 | $110.00 | $5.72 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 7.890000 | $9.40 | $74.17 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.300000 | $16.95 | $5.09 |
| GALVANIZADO POR INME | KG | 8.200000 | $3.00 | $24.60 | |
| Suma de Material | $158.92 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBA脩IL + 1 AYUDANTE DE ALBA脩IL) | JOR | 0.055560 | $576.23 | $32.02 |
| Suma de Mano de Obra | $32.02 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.070000 | $16.88 | $1.18 |
| Suma de Equipo | $1.18 | ||||
| Costo Directo | $192.12 |