| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.1 9 | CONTRATRABE DE CIMENTACION (TC6) INCLUYE CIMBRA Y DESCIMBRA SECCION 0.25 X 0.60 M REFORZADO CON 6 VARILLAS DE #5 Y 2 ADIC. #3, 3 BASTONES # 5 DE 4 ML Y 3 DEL # 5 DE 2 ML GALVANIZADA POR INMERSION EN CALIENTE CONCRETO F'C=250 KG/CM2-3/4", PREMEZCLADO, BOMBEADO VIBRADO Y CURADO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GALVANIZADO POR INME | KG | 14.560000 | $3.00 | $43.68 | |
| Suma de Material | $43.68 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 1.200000 | $72.29 | $86.75 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.014000 | $13,029.10 | $182.41 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.154500 | $1,181.25 | $182.50 |
| Suma de Concepto | $451.66 | ||||
| Costo Directo | $495.34 |