| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.2.2. 4 | NERVADURA EN ESTRUCTURA (N2) INCLUYE CIMBRA Y DESCIMBRA SECCION = 15 X35 CM REFORZADA CON 2 VAR. #3, Y 2 VAR. # 4, 1 BASTON # 3 DE 5 ML Y EST. # 2 @ 20 CMS DE ACERO FY'=4200 KG/CM2 CONCRETO PREMEZCLADO F'C=250 KG/CM2-3/4" BOMBEADO, VIBRADO Y CON ACELERANTE GALVANIZADO POR INMERSION EN CALIENTE | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 250 | CONCRETO PREMEZCLADO BOMBEABLE DE 250 KG/CM2, INCLUYE: CONCRETO CPO, REVENIMIENTO 12-14. | M3 | 0.053000 | $949.00 | $50.30 |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.053000 | $110.00 | $5.83 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 5.570000 | $9.40 | $52.36 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.250000 | $16.95 | $4.24 |
| GALVANIZADO POR INME | KG | 5.790000 | $3.00 | $17.37 | |
| Suma de Material | $130.09 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.040000 | $576.23 | $23.05 |
| Suma de Mano de Obra | $23.05 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.075000 | $16.88 | $1.27 |
| Suma de Equipo | $1.27 | ||||
| Costo Directo | $154.41 |