| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| LOSA-CIM | LOSA DE CIMENTACION DE 10 CMS DE ESPESOR ESTRUCTURADA CON TRABES DE 20X30 A BASE DE CONCRETO PREMEZCLADO DE 200KG/CM2 CON INCLUSION DE IMPERMEABILIZANTE INTEGRAL, ARMADA CON MALLA ELECTROSOLDADA 6-6/6-6, CON BASTONES DE VARILLA DEL No.3 DE 60 CMS @ 30 CMS EN EJES DE MUROS, INCLUYE PROTECCION DE BASE CON POLIETILENO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AIBFE092 | Festegral (pres 20kg) | kg | 0.750000 | $9.35 | $7.01 |
| CPAPR015 | Concreto premez. f'c=200 kg/cm2 RN,tma= 20mm, rev 10 clase 2 grd A no bombeable, marca Lacosa | m3 | 0.140000 | $845.00 | $118.30 |
| A1FAR020 | Malla electrosoldada 6x6/6-6 hoja, rollo de 100m2 | m2 | 1.100000 | $18.00 | $19.80 |
| 0084-00 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | KG | 1.169700 | $9.00 | $10.53 |
| 0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.100000 | $11.00 | $1.10 |
| AIIFE015 | Polietileno 800 x 0.40 m ancho. rollo de 100 m | m | 1.100000 | $5.70 | $6.27 |
| Suma de Material | $163.01 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.055556 | $783.11 | $43.51 |
| Suma de Mano de Obra | $43.51 | ||||
| Costo Directo | $206.52 |