| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| E.P. 03-28 | TRABES CAJON , DE 1.70 M DE PERALTE Y 38.802 M DE CLARO PRESFORZADAS DE CONCRETO DE F' C = 400 KG/CM2 | pzas |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRABE CAJON 28 | TRABES CAJON , DE 1.70 M DE PERALTE Y 38.802 M DE CLARO PRESFORZADAS DE CONCRETO DE F' C = 400 KG/CM2 | PZA | 1.000000 | $164,686.71 | $164,686.71 |
| Suma de Material | $164,686.71 | ||||
| Auxiliar | |||||
| AUXILIAR TRABE-01 | TRANSPORTE DE TRABE CAJON | M3 | 21.700000 | $182.29 | $3,955.69 |
| AUXILIAR MONTAJE-02 | MONTAJE DE TRABE | M3 | 21.700000 | $568.01 | $12,325.82 |
| Suma de Auxiliar | $16,281.51 | ||||
| Costo Directo | $180,968.22 |