| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 047M16 | Pozos de visita para subdrenes por unidad de obra terminada (EP.032-E02) | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACE4 | ACERO DE IGUAL O MAYOR DE DE F'C= 4000 KG/CM2 | KG | 13.910000 | $9.90 | $137.71 |
| A4BAR012 | Alambre recocido Calibre 18 | kg | 0.600000 | $9.60 | $5.76 |
| CIMBRA05 | CLAVO (VARIAS MED.) | Kg | 0.625600 | $25.20 | $15.77 |
| AGREGADO-06 | cemento gris | ton | 1.050000 | $1,586.20 | $1,665.51 |
| MAT20 | GRAVA LIMPIA PARA CONCRETO INCLUYE ACARREO | M3 | 1.000000 | $161.81 | $161.81 |
| MAT21 | ARENA INCLUYE ACARREO | M3 | 3.440000 | $146.85 | $505.16 |
| CIMBRA-04 | MADERA DE PINO | PT | 9.730000 | $6.07 | $59.06 |
| COMBUSTIBLE 01 | DIESEL | LT | 1.980000 | $7.24 | $14.34 |
| TABIQUE | TABIQUE ROJO | MILL | 1.000000 | $1,304.35 | $1,304.35 |
| Suma de Material | $3,869.46 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 2.000000 | $713.11 | $1,426.22 |
| Suma de Mano de Obra | $1,426.22 | ||||
| Auxiliar | |||||
| BASI"A" | EXCAVACION EN MATERIAL TIPO "A" | M3 | 1.100000 | $7.69 | $8.46 |
| BASAGUA | AGUA | M3 | 8.000000 | $14.30 | $114.40 |
| Suma de Auxiliar | $122.86 | ||||
| Costo Directo | $5,418.54 |