| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| N-CTR-CAR-1-01-002/0 | Trazo y nivelacion para desplante de estructuras con aparatos topograficos P.U.O.T. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CAL | CALHIDRA | TON | 0.000200 | $950.00 | $0.19 |
| DUELA | DUELA DE PINO DE 3a DE 3/4"X3.5"X8.25" | PZA | 0.020000 | $25.00 | $0.50 |
| MAHILO | HILO CANAMO | PZA | 0.001000 | $11.47 | $0.01 |
| 3. | VARILLA DE 3/8" 9.5MM | KG | 0.020000 | $9.85 | $0.20 |
| Suma de Material | $0.90 | ||||
| Mano de Obra | |||||
| 1T2E | CUADRILLA No. 27 (1 TOPOGRAFO + 2 AY.ESP.) | jor | 0.006000 | $850.33 | $5.10 |
| Suma de Mano de Obra | $5.10 | ||||
| Equipo | |||||
| EQTRAN | EQUIPO DE TOPOGRAFIA | hora | 0.050000 | $12.14 | $0.61 |
| Suma de Equipo | $0.61 | ||||
| Auxiliar | |||||
| 100. | CONCRETO DE F'c= 100 KG/CM2. HECHO EN OBRA, T.M.A=19 MM, RESISTENCIA NORMAL | M3 | 0.000500 | $650.65 | $0.33 |
| Suma de Auxiliar | $0.33 | ||||
| Costo Directo | $6.93 |