| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2014 | MURO DE BLOCK 15 x 20 40 CM. ASENTADO CON MORTERO CEMENTO ARENA 1: 4 . JUNTAS DE 1.5 CM. ACABADO COMUN. EN CIMENTACION | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BLOCK 15 X 20 X 40 | BLOCK 15 X 20 X 40 | M2 | 1.030000 | $84.00 | $86.52 |
| AGUA ACARREA INTERNO | 0 | M3. | 0.080000 | $30.00 | $2.40 |
| Suma de Material | $88.92 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.076920 | $859.49 | $66.11 |
| Suma de Mano de Obra | $66.11 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE. 1:5 | Mortero cemento arena 1:5 | M3 | 0.005000 | $714.41 | $3.57 |
| ANDAMIO METALIC3MTS | ANDAMIO DE 3 MTS DE ALTURA | DIA | 0.036000 | $50.64 | $1.82 |
| Suma de Auxiliar | $5.40 | ||||
| Costo Directo | $160.43 |