| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IP-OC-01 | SUMINISTRO Y ELABORACION DE REGISTRO PARA AGUAS PLUVIALES , INCLUYE: MATERIAL, MANO DE OBRA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA INSTALACION. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-006 | CEMENTO GRIS | TON | 0.168000 | $1,631.08 | $274.02 |
| REGISTRO-02 | MARCO Y CONTRAMARCO METALICO DE ANGULO 70X70 CM. | PZA | 1.000000 | $350.00 | $350.00 |
| Suma de Material | $624.02 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 1.700000 | $638.99 | $1,086.28 |
| Suma de Mano de Obra | $1,086.28 | ||||
| Auxiliar | |||||
| CONCRETO 150 KG/CM2D | CONCRETO DE F'C= 150KG/CM2 HECHO EN OBRA AGREGADO MAXIMO 3/4. | M3 | 0.030000 | $927.74 | $27.83 |
| MORTERO 1:5 | MORTERO CEMENTO ARENA 1:5, ELABORADO CON CEMENTO CPO-30-RS | M3 | 0.170000 | $689.42 | $117.20 |
| CONCRETO F`C=100 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2 AGREGADO MAXIMO 3/4, ELABORADO CON CEMENTO CPO-30-RS | M3 | 0.050000 | $858.48 | $42.92 |
| Suma de Auxiliar | $187.96 | ||||
| Costo Directo | $1,898.26 |