| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BCPCMR42 | CONSTRUCCION DE LOSA DE CONCRETO PREMEZCLADO MR=42 KG/CM2, T.M.A. 40MM. R.N. 10 (+/-2.5), INCLUYE: TENDIDO, VIBRADO CON REGLA VIBRATORIA, FLOTADO, ACABADO RAYADO, EQUIPO, MATERIALES, HERRAMIENTA Y MANO DE OBRA. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAT0101 | AGUA DE TOMA MUNICIPAL | m3 | 0.020000 | $25.00 | $0.50 |
| MAT0501 | CONCRETO PREMEZCLADO f'c=300 Kg/Cm2. | m3 | 1.050000 | $1,112.00 | $1,167.60 |
| Suma de Material | $1,168.10 | ||||
| Mano de Obra | |||||
| MO-1001 | AYUDANTE DE ALBAÑILERIA | jor | 0.266640 | $271.15 | $72.30 |
| MO-1000 | AYUDANTE GENERAL | jor | 0.080000 | $219.16 | $17.53 |
| JIMI100 | MANDO INTERMEDIO | (%)mo | 0.080000 | $0.00 | $0.00 |
| MO-1002 | OFICIAL DE ALBAÑILERIA | jor | 0.133320 | $361.11 | $48.14 |
| Suma de Mano de Obra | $137.98 | ||||
| Herramienta | |||||
| HEME-01 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQ103 | CAMION PIPA 8000 LTS INTERNATIONAL | hora | 0.003680 | $401.78 | $1.48 |
| EQ112 | REGLA VIBRATORIA | hora | 0.600000 | $42.57 | $25.54 |
| Suma de Equipo | $27.02 | ||||
| Costo Directo | $1,333.10 |