| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| GABIN003 | Gabinete para conexiones electricas, incluye: suministro y colocacion. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 11GAB003 | GABINETE PARA CONEXIONES | PZA | 1.020000 | $356.40 | $363.53 |
| Suma de Material | $363.53 | ||||
| Mano de Obra | |||||
| MOE05001 | OFICIAL ELECTRICISTA | JOR | 0.100000 | $401.97 | $40.20 |
| MOA05003 | AYUDANTE | JOR | 0.100000 | $245.43 | $24.54 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $64.74 | $3.24 |
| Suma de Mano de Obra | $67.98 | ||||
| Herramienta | |||||
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $64.74 | $1.29 |
| Suma de Herramienta | $1.29 | ||||
| Auxiliar | |||||
| BASIM003 | MEZCLA CEMENTO-ARENA 1:3 | M3 | 0.010000 | $1,510.95 | $15.11 |
| Suma de Auxiliar | $15.11 | ||||
| Costo Directo | $447.91 |