| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 020113 | Excavacion 8-10m para pilas material heterogeneo | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADMT | Cuadrilla Mvto de tierra | jor | 0.467130 | $107,037.00 | $50,000.19 |
| Suma de Mano de Obra | $50,000.19 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MOTOB01 | Motobomba | gl | 0.500000 | $1,100.00 | $550.00 |
| MOLINETE | Molinete | dÃa | 1.000000 | $2,088.00 | $2,088.00 |
| Suma de Equipo | $2,638.00 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 1.300000 | $5,000.00 | $6,500.00 |
| Suma de Auxiliar | $6,500.00 | ||||
| Concepto | |||||
| 160304 | Entibado temporal | m2 | 0.623200 | $9,298.00 | $5,794.51 |
| 020402 | Cargue (Paleros)-transp-botada. | m3 | 1.300000 | $27,048.00 | $35,162.40 |
| Suma de Concepto | $40,956.91 | ||||
| Costo Directo | $100,095.11 |