| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070106 | Muro 15 bloque concreto | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BLOQCON15A | Bloque concreto 15x20x40 | un | 13.125000 | $2,235.00 | $29,334.38 |
| Suma de Material | $29,334.38 | ||||
| Mano de Obra | |||||
| ZCUADMAM | Cuadrilla MamposterÃa | jor | 0.069000 | $116,803.00 | $8,059.41 |
| Suma de Mano de Obra | $8,059.41 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| OBRAFALSA | Obra falsa (alquiler) | dÃa | 0.243070 | $4,365.00 | $1,061.00 |
| CORTALADR | Cortadora de ladrillo / disco y operador | dÃa | 0.031579 | $87,620.00 | $2,766.95 |
| Suma de Equipo | $3,827.95 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.276000 | $1,000.00 | $276.00 |
| TRMAT | Transporte materiales | glo | 1.093000 | $1,000.00 | $1,093.00 |
| Suma de Auxiliar | $1,369.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.030000 | $285,872.00 | $8,576.16 |
| Suma de Concepto | $8,576.16 | ||||
| Costo Directo | $51,166.89 |