| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7.2.2.3.B | SUMINISTRO Y COLOCACIÓN DE CONCRETO HIDRAULICO F'C= 250 KG/CM2 AGREGADO MAXIMO 3/4" PREMEZCLADO INCLUYE: BOMBEO DE CONCRETO, CEMENTO, AGUA, AGREGADOS PÉTREOS, CIMBRA APARENTE, DESCIMBRADO, BOMBEO DE ACHIQUE CON BOMBA DE 4" DE DIAMETRO, VIBRADO, CURADO Y TODO LO NECESARIO PARA SU CORRECTA ELABORACIÓN Y COLOCACIÓN. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUAPOTA | agua | m3 | 0.500000 | $10.00 | $5.00 |
| CURACRETO | Curacreto blanco (Fester) | L | 0.246150 | $65.00 | $16.00 |
| BOMBEOC | Servicio de bomba | m3 | 1.050000 | $180.00 | $189.00 |
| CONCRETO 250 | CONCRETO PREMEZCLADO Fc=250 KG/CM2 | M3 | 1.050000 | $1,900.00 | $1,995.00 |
| CIMBRAPLAY | Cimbra play | M2 | 0.859380 | $128.00 | $110.00 |
| BARROTE | barrote | pt | 1.250000 | $8.90 | $11.13 |
| DIESEL1 | Diesel | L | 0.500000 | $8.45 | $4.23 |
| CLAVO | Clavo de 2-4 | kg | 0.070000 | $22.00 | $1.54 |
| ACERO2 | Alambre | kg | 0.010000 | $17.00 | $0.17 |
| REVEN | Reven. 14 CM | m3 | 1.050000 | $75.00 | $78.75 |
| Suma de Material | $2,410.81 | ||||
| Mano de Obra | |||||
| VILLA8 | Cuadrilla de albañil | Jor | 0.070700 | $1,048.80 | $74.15 |
| VILLA5 | Cuadrilla de carpinteria | Jor | 0.282790 | $1,048.80 | $296.59 |
| Suma de Mano de Obra | $370.74 | ||||
| Equipo | |||||
| EQ18 | Vibrador de chicote | Hora | 0.069280 | $113.58 | $7.87 |
| Suma de Equipo | $7.87 | ||||
| Costo Directo | $2,789.42 |